Dagoretti-Karen road expansion set to begin in August

ngong road

Ngong Road expansion. The government has awarded the Sh2 billion tender for the dualling of Ngong Road Phase III from Dagoretti Corner to Karen Shopping Centre. FILE PHOTO | NMG

The government has awarded the Sh2 billion tender for the dualling of Ngong Road Phase III from Dagoretti Corner to Karen Shopping Centre.

The 9.8-kilometre contract awarded to Chinese contractor, China Qinjian International Group (Kenya) Ltd, is set to start next month and run for two years.

Funding for the project has been sourced fully from the government through the Development Vote and covers three sections: Dagoretti Corner-Karen Roundabout (6.2km), Karen Road (1.9km) and a small section of Langata Road from Karen shopping centre (1.7km).

The Kenya Urban Roads Authority, which will oversee the project said the scope of works include 6.5 metre wide, two-lane carriageways, two roundabouts, one at Karen/Ngong road section and another one at the Karen/Lang’ata Road junction.

KURA Acting Director-General Silas Kinoti said the design will also include bus bays as well as non-motorised transport (NMT’s) – (footbridges, footpaths and cycle paths). Landscaping for preservation of the environment and beautification has also been incorporated in the design.

READ: Ngong Road work to delay for 5 months

“This dualling is intended to ease movement of traffic, improve urbanisation and bring economic growth especially to Karen and Ngong Town residents considering the unmatched development experienced in this part of Nairobi and Kajiado Counties,” Mr Kinoti said.

KURA said the project is part of the construction and infrastructure upgrades meant to elevate Nairobi City’s status and its environs and achieve the Vision 2030 objective of transforming the status of the country to a middle income economy.

READ: SA group plans 345 Ngong Road housing units

Three phases

Ngong Road, which is notorious for traffic snarl-ups, has a planned expansion in three phases.

The first phase (from Kenya National Library to Ring Road junction), is now 58 per cent done and is expected to be complete by November.

READ: First phase of Ngong Road expansion on course, says authority

Today, the Japanese government which is funding the Sh1.4 billion phase one is expected to sign a funding agreement with the National Treasury for the second phase (a three-kilometre stretch between Ring Road Kilimani and Dagoretti Corner) which is scheduled start early next year.

The first phase which runs for 2.57km and is also being built by Japanese firm World Kaihatsu Kogyo (WKK).

With many roadside businesses from furniture workshops, petrol stations, shops and flower sales set to be affected along the Dagoretti Corner and Lenana School stretch, KURA is now appealing for co-operation from the businesses who will be affected by the expansion.

Co-operation

“We ask members of the public currently doing business along the corridor to cooperate during the development of the project,” the agency said.

The Chinese contractor awarded the latest phase of the road expansion will be making its debut entry into the country where many other Chinese contractors have bagged lucrative contracts.

During the January bid announcement, Kura had indicated that the works would begin in July and would run concurrently with the second phase (which is now slated for next year).