Jomo Kenyatta University of Agriculture and Technology (Jkuat) will pay its former landlord three months’ rent on top of catering for the costs of renovating the building, amounting to Sh53.8 million after it closed its Nakuru campus in January 2021.
The Supreme Court awarded Kwanza Estates Limited three months’ rent amounting to Sh13.8 million and upheld an earlier payment of Sh40 million the company spent on renovating the premises in Nakuru.
The university shut down the campus in January 2021 after giving a three-month notice, citing a decline in student enrolment and the effects of the Covid-19 pandemic.
The firm, associated with businessman Geoffrey Asanyo, sued Jkuat for breach of contract after terminating the lease 14 months before the expiry.
A five-bench judge of the Supreme Court, presided by Justice Mohamed Ibrahim, ruled that where the parties are compelled to disengage without mutual agreement, either voluntarily or by eviction, it shall be deemed a breach of contract.
The judge also added that notwithstanding the absence of a termination clause, it would be unconscionable to compel a tenant to remain in premises they no longer wish to occupy.
“Equally, it would be unreasonable to claim rent for the unexpired lease term after the tenant has vacated. Therefore, the remedy for such termination is rent due up to the date of vacating and damages for breach of contract. In such a case, the remedy is for the party responsible for the breach to be liable to pay damages,” the judges said.
The Court of Appeal in June last year spared Jkuat from paying the rent, saying the impact of Covid-19 was beyond the control of the university. The court, however, directed the institution to pay Sh40 million in costs to the landlord for renovating the premises.
The appellate court had held that the pandemic was no secret, and the landlord was aware of the government directive to close schools and universities.
Court documents showed that the university and Kwanza Estates entered an agreement in 2016 to lease the building for a period of six years beginning in 2016.
Jkuat said it started experiencing dire financial constraints occasioned by reduced government support and a decline in the uptake of programs.
The Nakuru CBD Campus, the court heard, made severe losses and was unable to financially sustain itself, leading to its eventual shutdown.
The lower court judge said the agreement signed by the varsity and Kwanza Estates was binding and the parties were under obligation to discharge their duties until the end of its term. The High Court had ordered JKUAT to pay Sh110 million.
On appeal, Jkuat was directed to pay only Sh40 million for the renovation but not satisfied, Kwanza Estates moved to the Supreme Court.