Consumers to pay Sh5.7bn for wind power line delays

The Lake Turkana Wind Power project. FILE PHOTO | NMG

Kenya has agreed with the developers of Lake Turkana Wind Power project to charge electricity consumers Sh5.7 billion from next May as penalty for government’s failure to build a transmission line to the wind farm.

Energy principal secretary Joseph Njoroge said the deal was reached after months of negotiations with the foreign developers, their respective embassies and lenders, including the African Development Bank (AfDB).