SGR track laying process to be finalised in December
A section of the Standard Gauge Railway running through Makueni County. The Transport Ministry says only 35 per cent of the cargo handled at the Mombasa Port will be hauled via SGR. FILE PHOTO | SALATON NJAU
The laying of the 472km Standard Gauge Railway (SGR) line is expected to be complete by December with test runs beginning early next year.
The Transport and Infrastructure Ministry says that 234 kilometres of track-line have so far been laid between Emali and Voi.