Court clears Kwale mine shutdown with strict environmental conditions

Final mining activities at Base Titanium in Msambweni, Kwale County on May 7, 2024.

Photo credit: File | Nation Media Group

The Environment and Land Court has lifted orders halting the decommissioning of Base Titanium’s Kwale mine, allowing the exercise to proceed under strict environmental safeguards and regulatory oversight.

In a detailed ruling, the court set aside earlier conservatory orders issued in February that had stopped all dismantling and rehabilitation works at the Msambweni/Kinondo site. The court found that the stoppage posed greater environmental and safety risks than continuation.